Luis Munoz Marin 663 Broadway Newark, NJ 07104 |
Attendance Zone | State Code | NPS Code | School Type | Grade Structure | Gross Area | Construction Type |
North Region – East | 301 | 036 | E-M | PK-8 | 191,351 SF |
Date | Area | Perimeter | Stories | |
Original | 1955 | 191,351 SF | 6,822 FT | 4 |
Long Range Facilities Plan (LRFP)
Facility Condition (2013-02-04) | |
Facility Condition Index (FCI) % Score | 16 |
Facility Condition | Good |
FCI Deficiency Cost | $6,376,602 |
FCI Replacement Cost | $39,466,144 |
Click to access full Condition Report |
Capacity Utilization (2013-02-04) | |
2012-13 Enrollment | 956 |
Adjusted Capacity |
980 |
2012-13 Utilization |
98 |
Click to access full Capacity Report |
Educational (Facility) Adequacy (2013-02-04) | |
Classroom Adequacy % Score |
93 |
Classroom Adequacy |
Good |
Special Spaces Adequacy % Score |
91 |
Special Spaces Adequacy |
Good |
Click to access full Adequacy Report |
Energy Use (2013-04-10) | |
Gas Usage (Therms) |
69039 |
Electric Usage (kWh) |
940320 |
EUI/SF |
52.8 |
Click to access full Energy Use Report |